Location: Wanlip Sewage Treatment Works, Leicester
Project Value: Circa £420,000 (Excl. VAT)

In engineering, safe and reliable access is the foundation of every successful operation. Steelway recently completed the design, manufacture and installation of access metalwork at Wanlip Sewage Works, Severn Trent's third largest wastewater facility and the centre piece of its 2025 to 2030 investment period.
Working alongside principle contractor MWH Treatment, we provided perimeter walkways, a central platform and stairs for two new 37m diameter primary settlement tanks.

How do you build a walkway that follows a curve of around 116m?
Each support, floor panel and handrail section had to match the radius of its tank and fit precisely around precast concrete walls. The steelwork also needed to integrate seamlessly with other packages on a live, fast tracked works, while withstanding a corrosive wastewater environment.
"Wanlip is a landmark scheme for Severn Trent and the programme left no margin for error. Designing the whole access arrangement in 3D and keeping manufacture in-house meant we could respond quickly to changes on site and deliver steelwork that fitted first time"


The project not only gave Severn Trent's operators a dependable means of inspecting and maintaining the tanks but also led to a series of follow-on orders through to autumn 2026, a testament to the skill and commitment to everyone involved.
Discover the story behind the project in more depth, including the technical details, scope and timeline of works.
Download the Wanlip STW case study (PDF)
To learn more about our products and services, contact our team on 01902 451733 or email sales@steelway.co.uk
Location: Wanlip Sewage Treatment Works, Leicester
Project Value: Circa £420,000 (Excl. VAT)

In engineering, safe and reliable access is the foundation of every successful operation. Steelway recently completed the design, manufacture and installation of access metalwork at Wanlip Sewage Works, Severn Trent's third largest wastewater facility and the centre piece of its 2025 to 2030 investment period.
Working alongside principle contractor MWH Treatment, we provided perimeter walkways, a central platform and stairs for two new 37m diameter primary settlement tanks.

How do you build a walkway that follows a curve of around 116m?
Each support, floor panel and handrail section had to match the radius of its tank and fit precisely around precast concrete walls. The steelwork also needed to integrate seamlessly with other packages on a live, fast tracked works, while withstanding a corrosive wastewater environment.
"Wanlip is a landmark scheme for Severn Trent and the programme left no margin for error. Designing the whole access arrangement in 3D and keeping manufacture in-house meant we could respond quickly to changes on site and deliver steelwork that fitted first time"


The project not only gave Severn Trent's operators a dependable means of inspecting and maintaining the tanks but also led to a series of follow-on orders through to autumn 2026, a testament to the skill and commitment to everyone involved.
Discover the story behind the project in more depth, including the technical details, scope and timeline of works.
Download the Wanlip STW case study (PDF)
To learn more about our products and services, contact our team on 01902 451733 or email sales@steelway.co.uk
Location: Wanlip Sewage Treatment Works, Leicester
Project Value: Circa £420,000 (Excl. VAT)

In engineering, safe and reliable access is the foundation of every successful operation. Steelway recently completed the design, manufacture and installation of access metalwork at Wanlip Sewage Works, Severn Trent's third largest wastewater facility and the centre piece of its 2025 to 2030 investment period.
Working alongside principle contractor MWH Treatment, we provided perimeter walkways, a central platform and stairs for two new 37m diameter primary settlement tanks.

How do you build a walkway that follows a curve of around 116m?
Each support, floor panel and handrail section had to match the radius of its tank and fit precisely around precast concrete walls. The steelwork also needed to integrate seamlessly with other packages on a live, fast tracked works, while withstanding a corrosive wastewater environment.
"Wanlip is a landmark scheme for Severn Trent and the programme left no margin for error. Designing the whole access arrangement in 3D and keeping manufacture in-house meant we could respond quickly to changes on site and deliver steelwork that fitted first time"


The project not only gave Severn Trent's operators a dependable means of inspecting and maintaining the tanks but also led to a series of follow-on orders through to autumn 2026, a testament to the skill and commitment to everyone involved.
Discover the story behind the project in more depth, including the technical details, scope and timeline of works.
Download the Wanlip STW case study (PDF)
To learn more about our products and services, contact our team on 01902 451733 or email sales@steelway.co.uk
Location: Wanlip Sewage Treatment Works, Leicester
Project Value: Circa £420,000 (Excl. VAT)

In engineering, safe and reliable access is the foundation of every successful operation. Steelway recently completed the design, manufacture and installation of access metalwork at Wanlip Sewage Works, Severn Trent's third largest wastewater facility and the centre piece of its 2025 to 2030 investment period.
Working alongside principle contractor MWH Treatment, we provided perimeter walkways, a central platform and stairs for two new 37m diameter primary settlement tanks.

How do you build a walkway that follows a curve of around 116m?
Each support, floor panel and handrail section had to match the radius of its tank and fit precisely around precast concrete walls. The steelwork also needed to integrate seamlessly with other packages on a live, fast tracked works, while withstanding a corrosive wastewater environment.
"Wanlip is a landmark scheme for Severn Trent and the programme left no margin for error. Designing the whole access arrangement in 3D and keeping manufacture in-house meant we could respond quickly to changes on site and deliver steelwork that fitted first time"


The project not only gave Severn Trent's operators a dependable means of inspecting and maintaining the tanks but also led to a series of follow-on orders through to autumn 2026, a testament to the skill and commitment to everyone involved.
Discover the story behind the project in more depth, including the technical details, scope and timeline of works.
Download the Wanlip STW case study (PDF)
To learn more about our products and services, contact our team on 01902 451733 or email sales@steelway.co.uk
Location: Wanlip Sewage Treatment Works, Leicester
Project Value: Circa £420,000 (Excl. VAT)

In engineering, safe and reliable access is the foundation of every successful operation. Steelway recently completed the design, manufacture and installation of access metalwork at Wanlip Sewage Works, Severn Trent's third largest wastewater facility and the centre piece of its 2025 to 2030 investment period.
Working alongside principle contractor MWH Treatment, we provided perimeter walkways, a central platform and stairs for two new 37m diameter primary settlement tanks.

How do you build a walkway that follows a curve of around 116m?
Each support, floor panel and handrail section had to match the radius of its tank and fit precisely around precast concrete walls. The steelwork also needed to integrate seamlessly with other packages on a live, fast tracked works, while withstanding a corrosive wastewater environment.
"Wanlip is a landmark scheme for Severn Trent and the programme left no margin for error. Designing the whole access arrangement in 3D and keeping manufacture in-house meant we could respond quickly to changes on site and deliver steelwork that fitted first time"


The project not only gave Severn Trent's operators a dependable means of inspecting and maintaining the tanks but also led to a series of follow-on orders through to autumn 2026, a testament to the skill and commitment to everyone involved.
Discover the story behind the project in more depth, including the technical details, scope and timeline of works.
Download the Wanlip STW case study (PDF)
To learn more about our products and services, contact our team on 01902 451733 or email sales@steelway.co.uk